>>. The template must be cleaned and applied with release agent before each installation. The release agent must be applied evenly.
> > The welding and binding of guardrail steel bars must comply with the design and specification requirements, especially the location of the internally measured steel bars must be accurate.
> After the formwork is installed, check the side and top surfaces of the formwork. The sides and top surfaces of the formwork must be straight.
> >The area of the honeycomb pitted surface of the guardrail concrete shall not exceed the surface area, and the depth shall not exceed.
> > Single-sided guardrails within the same span should be poured at one time, and steel formwork should be used for the end formwork to ensure a flush appearance at the end.
> There should be no cracking at the guardrail surface and joints. Problems with misalignment, flatness, and appearance quality must be dealt with in a timely manner and the colors must be consistent. The top surface is smooth and beautiful, with consistent height.
> > The guardrail bridge's linear straight sections are straight, and the curved sections' arcs are smooth, without broken lines and dead corners.
The product specifications and models are complete and can be customized according to customer needs. New and old customers are welcome to come to discuss cooperation>!