Epoxy floor construction technology
Epoxy primer
Make sure the ground is clean before construction. If any debris adheres, it needs to be removed
Mix the epoxy resin and curing agent in the correct proportion
After stirring evenly, use a scraper or roller to apply.
Requires penetration to enhance adhesion.
Apply the epoxy mid-coat after the first coat is dry.
Epoxy mid-coat
Make sure the ground is clean before construction. If there is any debris adhering to it, it needs to be removed
Mix the epoxy resin and curing agent in the correct proportion. , and add a certain amount of quartz according to the proportion
Stir the sand evenly and pour it on the ground. Use a trowel to evenly trowel the material according to the designed thickness to increase the strength
And impact resistance makes the ground stronger and more resistant to pressure.
After the mid-coat layer dries, use sanding to smooth out the sagging particles on the surface.
Clean the dust.
Inspection method: Check whether the construction handover is properly handled. The skirting line is straight and smooth with no separation from the wall.
Epoxy putty layer
On a clean floor, mix the epoxy resin and quartz powder in the correct ratio and evenly scrape them on the floor with a trowel. To increase the bond between the mid-coat and the surface layer, and further adjust the flatness of the ground
Depending on the actual number of construction passes, it is required to be smooth without holes, without knife marks or sanding marks.
Inspection method: Make sure the ground is completely flat and without holes, and there are no knife marks or sanding marks before surface coating construction can be carried out.
Epoxy top coating
It needs to be kept clean before construction. If there is any debris adhering to it, it needs to be removed
Stir the components of the top coating material evenly first. Then add the curing agent and mix thoroughly
Use a roller to coat the material evenly
After the first coat is dry, apply the second top coat.
For self-leveling flat coating, use a trowel to scrape it once
Note that the coating at the junction of successive constructions must be even and without sagging.
Inspection method: The floor is smooth and even in color, without sagging or pinholes.